6500TPD Fauji Cement Plant (Green Field Project) -DG Khan
Client:
Fauji Cement Limited
Location:
DG Khan
Completion:
2024
Contract:
Main Contractor for Construction Of Cement Plant Civil Works
• Main Plant Building Areas Including Clay/additive crusher , gypsum Crusher & transport, Raw Mill area(feeder building, Cyclone building, Bag filter building), Preheater, SP Boiler, E& D Frame, Kiln Piers, Coal Grinding Mill, Clinker Cooler & Bag Filter, AQC Boiler, Water circulation Tanks, , Limestone pre-blending yard & Transport, Additive & Clay pre-blending yard & Transport, Cement Grinding Mills(Vertical Mill, Feeder building, Bag filters, ID Fan foundations), Packing and dispatch, Cement bulk loading building, Silo roof slabs, compressed air stations, Electric sub-stations, Cable trenches and Tunnels, conveyor transfer structures foundation and transfer towers, weigh bridges etc.
• Finishing works including Floor tiling, Painting, fall Ceiling works, Door/windows, of all utility building.